|
NRCS recently completed Emergency Watershed
Protection (EWP) work along the banks of North Chickamauga Creek in
northern Hamilton County, Tennessee. The project, consisting of 950 feet
of 12’ high gabion wall and more than 7900 tons of riprap, is one of the
largest gabion structures designed and built by NRCS in Tennessee.
Construction of the project began October 2005 and finished in January
2006. The site is located next to the Willow Creek subdivision and
Soddy-Daisy Industrial Park in Soddy-Daisy, about 17 miles north of
Chattanooga.

Background
In February of 2003, the weather service recorded
8.6 inches of rain for the month- the average is usually 4.9 inches.
This was not the first time the area had experienced heavy rains, but it
was after a particularly heavy down pour the situation for residents and
businesses along North Chick began to look dire. The attention of the
local media was drawn to the Willow Creek subdivision home of Diane
Halstead-Renz. The back porch of her house, precariously dangling over
the creeks edge, became a symbol of the situation.
For a number of years Willow Creek residents near
the creek had sought assistance through various local, state and federal
means. At one point an actual proposal had been designed and presented
by the U.S. Army Corps of Engineers. However due to cost issues, nothing
was ever implemented. After the 2003 winter rains officials with
Soddy-Daisy contacted the local USDA-NRCS office and requested
assistance through the agency’s EWP program.
Congressional funding for this project was approved
in September of 2004.

Design and Construction
The EWP project actually consisted of two
subprojects: construction of a low-flow channel and construction of the
gabion wall/placement of riprap.
§
Low Flow Channel
The low flow channel was installed with the hopes of diverting water
from the construction area while at the same time establishing a “pilot”
channel within the channel. The pilot channel was designed to
approximately carry the rain from a two year storm event. It has a
trapezoidal cross-section with a top width of 50 feet. The channel
actually passes under Dayton Pike, a high traffic two lane bridge and
outlets just downstream of the project area. The low flow channel is
2780 feet long.
The low flow channel
was dug starting at the downstream end and working up towards the
upstream project work limits. Creek rock was removed and taken off site.
Two weirs were placed in the low flow channel. Several large rocks were
left in the low flow channel to aid in aquatic habitat formation.
§
Gabion Wall and Riprap
The gabion retaining wall was designed using an approach that
considered different storm events and the “worse case” for stabilty. In
the end, the top elevation of the wall was determined by considering the
flood level during the 25 year storm. Because of the unique features of
the creek in the project area, the top elevation for the 25 year storm
event is actually very close to 100 year storm event elevation. The wall
was analyzed for stability under the “worse case” scenario.
The location for the
bottom of the wall was determined by looking at channel cross sections,
about 50 feet apart, going from the upper end of the wall towards the
end. And based on previous experience with gabions in dynamic channels,
the wall was located three feet below the lowest point shown on the
cross sections.
Before gabion walls were
selected as the stabilization method, cross-section analysis was used to
determine if large riprap could be placed on the banks instead. Due to
concerns over cost and the potential mobility of the computationally
sized riprap, it was decided that the gabion wall would, in the long
run, better withstand the forces of the channel. Rock riprap was placed
above the wall, to protect the structure from over topping and to tie
the wall to the banks.

Comments and Reactions
Ricky Dent, Willow Creek Resident
“During the first storm I
lost 35 feet from my yard and in the next rain I lost 25 more [feet]. I
was in immediate danger of loosing my house. The next storm would
certainly have caused me problems.
“Time will tell…but I
think it looks good! NRCS did a great job- their inspector made sure the
contractor did what he said he would do.”
Janice Cagle, City Manager, Soddy-Daisy,
Tennessee
“I don’t think we could
have gotten through the permitting process with out the help of NRCS.
The working relationship with NRCS has been great; they made everything
easy for me from beginning to the end.
“I’m sure that federal
officials don’t realize how important this fund is to small communities.
I know what a benefit the program has been to Soddy-Daisy, I can only
imagine what a benefit it is to other communities through out the United
States.”
Denise Watkins, Project Engineer, Chattanooga,
Tennessee
“The project was a great
success- the low flow channel served its’ main purpose and allowed us to
construct the wall over the winter months without many water problems.
“ In addition, the
Tennessee Department of Environment and Conservation and the Corps of
Engineers were very involved and helped out by working with us to
overcome obstacles that would have prevented the project from being
completed.”
Quick Facts
|
Quick Facts |
| Project Partners |
City of Soddy-Daisy, Hamilton County Soil Conservation
District |
| Contractor |
Steele and Associates, Alpharetta, Georgia |
| Low Flow Channel |
2780’ x 50' (variable depth) |
| Gabion Wall |
950’ in Length, 12’ High, 4817 Cubic Yards of Gabion
Stone |
| Geotextile |
19000 Square Yards |
| Construction Start Date |
10/3/2005 |
| Construction End Date |
1/23/2006 |
| Lead Designer |
Denise Watkins, Supervisory Civil Engineer |
| Contract Type |
Federal (25% Local Match) |
| Cost |
$1,597,791.53 |
Links of Interest
In The Wake of Ivan, Chattanooga Times Free Press
North Chickamauga
Creek Conservancy
|